Question: ( a ) Draw the precedence network. ( b ) What is the probability that the project can be c 4 npleted in 2 4
a Draw the precedence network.
b What is the probability that the project can be cnpleted in days or less? In days or less?
c Suppose that now is the end of the seventh day and that activities a & b have been completed while activity is percent completed. Threepoint estimates for the remaining duration of activity are now and days. Activities and are ready to begin. Determine the probability of finishing the project by the end of a day and b day
Duration in Days
tableActivityPrecedes,Optimistic,Most Likely,Pessimistica cb hc WWed fEnd,fggEnd,ii End,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
