Question: ( a ) Draw the precedence network. ( b ) What is the probability that the project can be c 4 npleted in 2 4

(a) Draw the precedence network.
(b) What is the probability that the project can be c4npleted in 24 days or less? In 21 days or less?
(c) Suppose that now is the end of the seventh day and that activities a & b have been completed while activity d is 50 percent completed. Three-point estimates for the remaining duration of activity d are now 5,6, and 7 days. Activities c and h are ready to begin. Determine the probability of finishing the project by the end of (a) day 24 and (b) day 21.
Duration in Days
\table[[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[a ....,c,5,6,7],[b ...........,h,8,8,11],[c WW........,e,6,8,11],[d ........,f,9,12,15],[,End,5,6,9],[f,g,5,6,7],[g...........,End,2,3,7],[h.......,i,4,4,5],[i ............,End,5,7,8]]
 (a) Draw the precedence network. (b) What is the probability that

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!