Question: please draw pert chart and answer in detail A manufacturing company is planning to use PERT to setup a project for a new production line.

please draw pert chart and answer in detail please draw pert chart and answer in detail A
A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the following activities, precedence relationships, and time estimates in days: Most Expected Immediate Optimistic Likely Pessimistic Duration Activity Predecessors a 10 12 10 7 9 7.17 m b 3 compoan 10 7.17 15 a. Draw a PERT network b. What is the probability that the project will be completed in less than 45 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock