Question: ( a ) Draw the project network. Use activity on node ( A - O - N ) method. ( b ) Calculate the length

(a) Draw the project network. Use activity on node (A-O-N) method.
(b) Calculate the length and variance of the Critical Path.
(c) Identify the non-critical activities! Work out the Total Slack (TS) and Free Slack (FS) for
all the non-critical activities.
(d) State whether the network is sensitive or insensitive!
(e) What is the approximate probability that jobs on the critical path will be completed by the
due date of (i)35 days, (ii)41 days?
3+1+2+1+5=12
 (a) Draw the project network. Use activity on node (A-O-N) method.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!