Question: A dress-making operation is being designed as an assembly line. The table below shows the tasks that need to be performed, their task times, and
A dress-making operation is being designed as an assembly line. The table below shows the tasks that need to be performed, their task times, and preceding tasks. If the goal is to produce 30 dresses per hour, answer the questions.
| Dress-Making Task Information | ||||
|---|---|---|---|---|
| Work Element | Immediate Predecessor | Task Time (sec) | ||
| A. Cut dress body | None | 29 | ||
| B. Cut sleeves | None | 40 | ||
| C. Cut collar | None | 18 | ||
| D. Sew dress body | A | 100 | ||
| E. Sew sleeves to dress | B, D | 24 | ||
| F. Sew collar to dress | C, D | 50 | ||
| G. Hem dress | D,E, F | 50 | ||
| H. Package dress | G | 92 | ||
Compute the cycle time.
C = enter cycle time in seconds per dress seconds/dress
eTextbook and Media
Which task is the bottleneck?
Task select a bottleneck task FCEGHDAB is the bottleneck.
eTextbook and Media
What is the maximum output for this line?
Maximum Output = enter maximum output in dresses per hour dresses per hour.
eTextbook and Media
Compute the theoretical minimum number of stations. (Round your answer up to the nearest whole number.)
TM = enter theoretical minimum number of stations rounded to the nearest whole number stations.
eTextbook and Media
Assign work elements to stations, using the longest task time rule.
| Work Station | Task Selected |
|---|---|
| select a work station 42351 | select a task HEFBGDAC |
| select a work station 51243 | select a task CEBFAHGD |
| select a work station 23451 | select a task AHEGBDCF |
| select a work station 32415 | select a task BHGACEFD |
| select a work station 25341 | select a task HEAFDGBC |
| select a work station 41532 | select a task ECFAHDBG |
| select a work station 32415 | select a task FBHEADCG |
| select a work station 31425 | select a task ACGEDBHF |
eTextbook and Media
Compute the efficiency and balance delay of your assignment. (Round your answers to 2 decimal places, the tolerance is +/-0.05)
| Efficiency | = | enter efficiency in percentages rounded to 2 decimal places % |
|---|---|---|
| Balance Delay | = | enter balance delay in percentages rounded to 2 decimal places % |
eTextbook and Media
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts