A drywall contractor is working on a project with 9 activities as shown below:
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Predecessor | - | - | 1 | 1,2 | 1,2 | 3 | 4,5 | 5,7 | 6,8 |
| Duration | 2 | 3 | 5 | 2 | 4 | 8 | 1 | 6 | 2 |
Construct CPM network for this project, compute the Early Start, Early Finish, Late Start and Late Finish dates, and identify the critical path(s)