Question: Question 6 (20 points) [20 Marks) A drywall contractor is working on a project with 9 activities as shown below: 2 3 4 5 6
Question 6 (20 points) [20 Marks) A drywall contractor is working on a project with 9 activities as shown below: 2 3 4 5 6 9 Activity 1 Predecessor Duration 2 3 1 5 1,2 2 1,2 4 7 4,5 1 8 5,7 6 3 6,8 2 8 Construct CPM network for this project, compute the Early Start, Early Finish, Late Start and Late Finish dates, and identify the critical path(s)