Question: A fabrication plant operates a single process technology with the following data: Layer Actual CT Std Dev of Actual CT Standard CT 1 2
A fabrication plant operates a single process technology with the following data:
Layer Actual CT Std Dev of Actual CT Standard CT
Layers through end with a photo step, while layer ends at fab out.
In a computer simulation of the plant, the average number of lots being processed at any given
time was
aWhat was the average active WIP level in the simulation?
bWhat production rate was assumed in the simulation?
cAssume the target cycle time is days and the production rate is the same as in
the simulation. Recommend target WIP levels by layer.
d Suppose there are two hour shifts per day and suppose actual WIP distribution
at the start of a shift is as follows:
Step by Step Solution
There are 3 Steps involved in it
To solve this problem well need to use the Littles Law which states that the average number of items ... View full answer
Get step-by-step solutions from verified subject matter experts