Question: A fabrication plant operates a single process technology with the following data: Layer Actual CT Std Dev of Actual CT Standard CT 1 2

A fabrication plant operates a single process technology with the following data:

Layer Actual CT Std Dev of Actual CT Standard CT

1 2.3 0.9 1.4

2 2.0 0.8 1.2

3 2.4 1.1 1.3

4 2.2 1.1 1.1

5 2.1 0.9 1.3

6 1.4 0.5 0.9

Layers 1 through 5 end with a photo step, while layer 6 ends at fab out.

In a computer simulation of the plant, the average number of lots being processed at any given

time was 72.

(a) What was the average active WIP level in the simulation?

(b) What production rate was assumed in the simulation?

(c) Assume the target cycle time is 12 days and the production rate is the same as in

the simulation. Recommend target WIP levels by layer.

(d) Suppose there are two 12-hour shifts per day and suppose actual WIP distribution

at the start of a shift is as follows:


Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem well need to use the Littles Law which states that the average number of items ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!