Question: A facility makes a product that has a manufacturing process consisting of tasks A, ... , H and requires that these be completed in an
A facility makes a product that has a manufacturing process consisting of tasks A, ... , H and requires that these be completed in an order that obeys a set of precedence requirements. The following table gives the performance time in minutes/unit and the preceding task(s) for tasks A, ... , H.
| Task | Completion Time (minutes/unit) | Predecessor Tasks |
|---|---|---|
| A | 5 | N/A |
| B | 6 | N/A |
| C | 9 | A,B |
| D | 4 | C |
| E | 10 | D |
| F | 9 | D |
| G | 8 | E, F |
| H | 1 | G |
The tasks have been assigned to 3 workstations: Station 1 performs tasks A and B; Station 2 performs tasks C, D, and E; Station 3 performs tasks F, G, and H.
What is cycle time for this configuration?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts