Question: A factory makes a product that has a manufacturing process consisting of tasks A , . . . , J that must be completed in

A factory makes a product that has a manufacturing process consisting of tasks A,..., J that must be completed in an order that obeys a set of precedence requirements. The following table reports the performance time in minutes/unit and the preceding task(s) for tasks A,..., J.
The precedence network is:
The line will operate for 480 minutes per shift. The desired shift output is at least 22 units.
The configuration Station 1(ABC); Station 2(DEF); Station 3(GH); Station 4(IJ) Select one: Meets the desired output Does not meet the desired output Violates a precedence requirement
The configuration Station 1(ABF); Station 2(CD); Station 3(EGH); Station 4(IJ) Select one: Meets the desired output Does not meet the desired output Violates a precedence requirement
The configuration Station 1(AFG); Station 2(HIJ); Station 3(BC); Station 4(DE) Select one: Meets the desired output Does not meet the desired output Violates a precedence requirement \begin{tabular}{|c|c|c|}
\hline Task & Performance Time & Preceding Tasks \\
\hline \hline A & 6 & NA \\
\hline \hline B & 6 & A \\
\hline \hline C & 9 & B \\
\hline \hline D & 3 & B \\
\hline \hline E & 4 & C, D \\
\hline \hline F & 13 & A \\
\hline \hline G & 3 & F \\
\hline \hline H & 2 & G \\
\hline \hline I & 2 & E, H \\
\hline \hline J & 3 & I \\
\hline \hline
\end{tabular}
The precedence network is:
 A factory makes a product that has a manufacturing process consisting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!