Question: A factory makes a product that has a manufacturing process consisting of tasks A , dots, J that must be completed in an order that
A factory makes a product that has a manufacturing process consisting of tasks dots, that must be completed in an order that obeys a set of precedence
requirements. The following table reports the performance time in minutesunit and the preceding tasks for tasks A J
The precedence network is:
The line will operate for minutes per shift. The desired shift output is at least units.
The configuration Station ABC; Station DEF; Station GH; Station IJ
The configuration Station ABF; Station CD; Station EGH; Station IJ
The configuration Station AFG; Station HIJ; Station BC; Station DE