Question: A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the
A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do? Meet with the project sponsor to discuss the feature with the product owner. Perform a risk analysis and then meet with the project sponsor to discuss it. Give all the work packages parallel priority and continue activities. Push back on the feature because it is not an immediate priority
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
