Question: A: Fill in the table below: Lead time = 1 week Demand Time Fence is at the end of Week #3 MPS Lot Size =

A: Fill in the table below:

Lead time = 1 week

Demand Time Fence is at the end of Week #3

MPS Lot Size = 50

On-Hand is 50

Week

1 2 3 4 5 6

Forecast 30 22 27 25 32 29

Customer Orders 28 23 27 27 31 26

PAB

50

MPS

ATP

B: Sales received the following customer requests (Quantity Below), in sequence, at the start of week 1.Using the information in the MPS record above, indicate to Sales (with a 'yes' or 'no') whether a delivery commitment can be made to a customer. Fill in the table below:

Week Commitment Quantity Response to Sales(Yes/No)

1 15

2 20

3 35