Question: Using the MPS record created in Question 1 and shown below, as well as the Bill of Materials (BOM) shown below, complete the two MRP

  • Using the MPS record created in Question 1 and shown below, as well as the Bill of Materials (BOM) shown below, complete the two MRP records by filling in the yellow cells.
  • If the answer is zero (0), enter a 0 in the cell.
  • Remember, FOQ is Fixed Order Quantity and L4L is Lot for Lot.
  • SHOW YOUR WORK! I need to see the MRP chart, and show how you got each number if you want partial credit. Otherwise, if a number is wrong it is wrong!

MPS Record and Bill of Materials (BOM):

For every (1) Item A you need (1) Item D and (4) Item E.

A (1)

D (1) E (4)

LT = 3 weeks LT= 2 weeks

Item: A

Lot Sizing Rule: FOQ = 100

Lead time: 1 week

Beginning Inventory: 80

Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 25 25 25 25 30 30 30 30 35 35 35 35
Projected On Hand (80) 55 30 5 80 50 20 90 60 25 90 55 20
Planned Orders (MPS) 0 0 100 0 0 100 0 0 100 0 0 0

Complete These Two MRP Records:

Item: D

Lot Sizing Rule: FOQ = 144

Lead Time: 3 weeks

Parent: A

Beginning Inventory: 120

Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 0 0 100 0 0 100 0 0 100 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0
Projected On Hand (120)
Planned Orders (MRP)
Planned Order Releases (MRP Release Date)

Item: E

Lot Sizing Rule: L4L

Lead Time: 2 weeks

Parent: A

Beginning Inventory: 0

Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 0 0 400 0 0 400 0 0 400 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0
Projected On Hand (120)
Planned Orders (MRP)
Planned Order Releases (MRP Release Date)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!