Question: A finish - to - start dependency indicates that: ( CLO 6 ) a . The completion of the successor activity depends on the completion

A finish-to-start dependency indicates that: (CLO6) a. The completion of the successor activity depends on the completion of the predecessor. b. The start of a successor depends on the start of the predecessor. Oc. A second activity cannot be started until the first activity has been completed. Od. The completion of the successor activity depends on the beginning of the predecessor.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!