A firm is planning a project for the development of a new product. The network of activities and data are shown below. What is the project duration?
Activity | Immediate Predecessor | Time (weeks) |
A | - | 2 |
B | A | 5 |
C | A | 4 |
D | B | 5 |
E | B, C | 6 |
F | D, E | 3 |