Question: A firm uses a serial assembly system and needs answers to the following: a. An output of 880 units per shift (8.00 hours) is desired

A firm uses a serial assembly system and needs answers to the following:

a. An output of 880 units per shift (8.00 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 32 seconds. What is the required cycle time for such a system? (Round your answer to the nearest whole number.)