Question: A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its intermediate period), it estimates the sum of demands to
A firm uses graphical techniques in its aggregate planning efforts. Over the next twelve months (its intermediate period), it estimates the sum of demands to be 90,000 units. The firm has 200 production days per year. In January, which has 25 production days, demand is estimated to be 10,000 units. Which of the following is correct?
- A. the January requirement is below level production of 450 units
- B. level production is approximately 500 units per month
- C. level production of 350 units per day is below the January requirement
- D. level production is approximately 500 units per day
- E. the firm must hire workers between December and January