Question: A) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion
A) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. What is the optimal sequence?
| Job | Processing Time (Days) | Due Date |
| A | 8 | 12 |
| B | 4 | 9 |
| C | 3 | 6 |
| D | 7 | 7 |
| E | 5 | 20 |
a) C - B - E - D - A
b) A - B - C - D - E
c) C - D - B - A - E
d) E - A - B - D - C
B) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. What is the average flow time?
| Job | Processing Time (Days) | Due Date |
| A | 10 | 12 |
| B | 4 | 9 |
| C | 3 | 6 |
| D | 7 | 7 |
| E | 5 | 20 |