Question: A) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion

A) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. What is the optimal sequence?

Job Processing Time (Days) Due Date
A 8 12
B 4 9
C 3 6
D 7 7
E 5 20

a) C - B - E - D - A

b) A - B - C - D - E

c) C - D - B - A - E

d) E - A - B - D - C

B) Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. What is the average flow time?

Job Processing Time (Days) Due Date
A 10 12
B 4 9
C 3 6
D 7 7
E 5 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock