Question: Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are

Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table.

Job

Processing Time (days)

Days Due from Today

A

6

11

B

7

16

C

5

15

D

3

10

E

2

12

Using the shortest processing time (SPT) rule, it can be concluded that the average lateness for the five jobs is:

a. more than -6 but less than or equal to -2 days.
b. more than -2 but less than or equal to 2 days.
c. more than 2 but less than or equal to 6 days.
d. more than 4 but less than or equal to 8 days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!