Question: A flood will require mining operations to cease for at least six months. How would a force majeure clause affect the status of the miner's

A flood will require mining operations to cease for at least six months. How would a force majeure clause affect the status of the miner's obligations relating to its existing supply contracts? a. Performance will be suspended until a specified event occurs. b. Non-performance of the contract will be excused without penalty. c. The innocent party will have the right to terminate and sue for breach