Question: A flood will require mining operations to cease for at least six months. How would a force majeure clause affect the legal status of

A flood will require mining operations to cease for at least six

A flood will require mining operations to cease for at least six months. How would a force majeure clause affect the legal status of the miner's obligations relating to its existing supply contracts? A) performance obligations will be suspended until a specified event occurs B) the innocent party will have the right to sue for damages for breach C) the innocent party will have the right to terminate and sue for breach OD) non-performance of the contract will be excused without liability