Question: a. For the schedule in Table 3, draw your baseline plan by using PDM/CPM node network, perform the CPM calculation, and mark the critical path.

a. For the schedule in Table 3, draw your

a. For the schedule in Table 3, draw your baseline plan by using PDM/CPM node network, perform the CPM calculation, and mark the critical path. Table 3: Tabulation of events ACTIVITY DURATION (Days) IPA Lag A 2 B 5 A 6 A D 6 B E 7 B F 4 B, C G 5 H 10 D, E, F 2 I 8 E, F, G J 7 D K 1 H, J