Question: A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Determine the processing sequence

A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Determine the processing sequence using SPT, EDD and CR. For each sequence compute the average job tardiness and average flow time at the work center.
\table[[Job,Job time (days),Due Date (days)],[a,4.5,10],[b,6,17],[c,5.2,12],[d,1.6,27],[e,2.8,18],[f,3.3,19]]