Question: A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown,
a. Determine the processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each sequence, compute the average job tardiness, the average flow time, and the average number of jobs at the work center. The list is in FCFS order.
b. Using the results of your calculations in part a, show that the ratio of average flow time and the average number of jobs measures are equivalent for all four sequencing rules.
c. Determine the processing sequence that would result using the S/ Orule.
.png)
Job Time ue Operations Job (days) Date Remaining 4.5 6.0 5.2 1.6 2.8 3.3 10 17 12 27 18 19
Step by Step Solution
3.40 Rating (163 Votes )
There are 3 Steps involved in it
a Determine the processing sequence using 1 FCFS 2 SPT 3 EDD and 4 CR For each sequence computer the average tardiness the average flow time and the average number of jobs at the work center 1 FCFS Se... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
372-B-M-L-O-M (3452).docx
120 KBs Word File