Question: A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown,
A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown, do the following:
| Job | Job Time (Days) | Due Date | Operations Remaining |
| a | 4.5 | 10 | 3 |
| b | 6.0 | 17 | 4 |
| c | 5.2 | 12 | 3 |
| d | 1.6 | 27 | 5 |
| e | 2.8 | 18 | 3 |
| f | 3.3 | 19 | 1 |
a-1. Determine the processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio.
Sequence for first come first serve: _____
Sequence for shortest processing time: _____
Sequence for earliest due date: _____
Sequence for critical ratio: _____
a-2. For each sequence, compute the average job tardiness, the average flow time, and the average number of jobs at the work center. The list is in First come, first served order. (Round your intermediate calculations and final answers to 2 decimal places.)
| first come first serve: | shortest processing time | earliest due date: | critical ratio: | |
| avg job tardiness | ||||
| avg flow time | ||||
| avg number of jobs |
b. Using the results of your calculations in part a, show that the average flow time and the average number of jobs measures are equivalent for all four sequencing rules. (Hint: Calculate the ratio of average flow time and the average number of jobs for each rule.) (Round your answer to 2 decimal places.) The ratio is aproximately ______
c. Determine the processing sequence that would result using the Slack per operation rule. The sequence is _____