Question: A formal CPM analysis for a project shows the planned costs to date are $65,000, and the accounting department reports charges to the job of

A formal CPM analysis for a project shows the planned costs to date are $65,000, and the accounting department reports charges to the job of $75,000. If the reported earn value to date is $70,000, the cost and schedule status of the project are most nearly-Ahead of schedule and over budget-Bchind schedule and over budgetAhend of schedule and under budgetBehind schedule and under badgetWhich of the following is NOT a direct benefit of formal schedules?-Provides time information-Ensures Safety-Forces detailed thinkingOlmproves communication