Question: A four station line with multi machine stations where the number of parallel machines at stations 1 , 2 , 3 and 4 respectively are

A four station line with multi machine stations where the number of parallel machines at stations 1,2,3 and 4 respectively are 6,5,3, and 2. The average processing times at stations 1,2,3, and 4 are 6,30,10, and 4 minutes. Draw the production line, compute the capacity in parts per hour of each station, find the bottleneck, and give the line throughput (assume WIP > critical WIP)