Question: a. From the following information, draw the project network. b. Identify the critical path. c. Draw Gantt Diagram. d. Interpret the Gantt Diagram. e. Integrate

a. From the following information, draw thea. From the following information, draw the project network. b. Identify the critical path. c. Draw Gantt Diagram. d. Interpret the Gantt Diagram. e. Integrate two project, calculate the coworker that we need to complete the projects in determined time. Explain your steps.

PROJECT-1 Time Activity (day) A 5 B 10 C 15 D 5 E 20 F 15 G 10 H 20 IE 420 PROJECT MANAGEMENT PROJECT IV Finish-to-Start Finish-to-Start Lag Lag Relationships Relationships 0 A 0 A 0 5 0 0 10 0 B B D C F Extra Lag Relationships Start-Finish C D Start-Start D E Finish-Finish D E Finish-Finish E F Finish-Finish G F Lag 0 0 20 5 25 0 0 10 0 PROJECT-1 Time Activity (day) A 5 B 10 C 15 D 5 E 20 F 15 G 10 H 20 IE 420 PROJECT MANAGEMENT PROJECT IV Finish-to-Start Finish-to-Start Lag Lag Relationships Relationships 0 A 0 A 0 5 0 0 10 0 B B D C F Extra Lag Relationships Start-Finish C D Start-Start D E Finish-Finish D E Finish-Finish E F Finish-Finish G F Lag 0 0 20 5 25 0 0 10 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!