Question: what do you mean by computer? IE 420 PROJECT MANAGEMENT PROJECT-I Finish-to-start lag ID Duration Additional lag relationships Lag A B D E 2 4

what do you mean by computer? IE 420 PROJECT

what do you mean by computer?

IE 420 PROJECT MANAGEMENT PROJECT-I Finish-to-start lag ID Duration Additional lag relationships Lag A B D E 2 4 6 8 18 Finish-to-start predecessor None A A B D F None E GH Kassevol None None Fihish-finish C to F None Finish-finish Eto G 0 0. 7 0 9 0 0 0 0 0 10 0 0 0 0 0 F G H 2 5 5 14 15 None Start-start G to H None Finish-finish I to J None 10 0 5 a. From the following information, draw the project network, b. Identify the critical path. c. Draw Gantt Chart d. Interpret the Gantt Diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!