Question: A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5
A future construction project has the following activity relationships and activity time estimates (in days):
| Activity | Immediate Predecessor | To | Tm | Tp |
| A | None | 4 | 5 | 6 |
| B | None | 3 | 6 | 21 |
| C | B | 1 | 4 | 7 |
| D | A | 2 | 5 | 8 |
| E | C, D | 3 | 6 | 15 |
| F | C | 3 | 9 | 21 |
| G | E, F | 2 | 4 | 6 |
| H | F, G | 2 | 2 | 2 |
Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as 4.32
Please calculate the "expected finish time" and "variance" for each activity.
What is the expected finish time of activity F?
What is the activity variance of activity F?
Use "expected finish time" of each activity to construct the network. What is the critical path of the project?
What is the expected project completion time in days?
What is the variance of project completion time?
Use "expected finish time" to decide ES, EF, LS, LF of each activity. What is the LS time of activity E?
What is the slack time of activity D?
Step by Step Solution
3.34 Rating (148 Votes )
There are 3 Steps involved in it
SOLUTION To calculate the expected finish time and variance for each activity we can use the formula ... View full answer