Question: A Gantt Chart depicts the dependencies between various activities better than network diagrams for complex projects. True False Which of the following is not an
A Gantt Chart depicts the dependencies between various activities better than network diagrams for complex projects. True False
Which of the following is not an example of benchmarking?
|
|
Dell learning JIT/Lean principles from Toyota
|
|
|
Amazon trying to lure supply chain employees from Walmart
|
|
|
Eberly Management Department learning best practices in advising from another department.
|
|
|
GM trying to do as well as Ford in Inventory Turns
|
Taiichi Ohno was able to reduce the lot size in the stamping operation at Toyota because he was able to reduce the setup time from 6.5 hours to 28 minutes with the help of Shingo.
| True | |
| False |
While defining a project, which of the following is NOT important?
Question 29 options:
|
|
Task precedence relationship or task interdependence
|
|
|
Cost, time and human resources required
|
|
|
Inventory costs that are going to be incurred
|
|
|
Tasks/activities/sub-tasks for the project (work breakdown schedule)
|