Question: A Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ESEF LSLF SLACK 3

A Given the following partially completed Project
A Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ESEF LSLF SLACK 3 0 30 30 8 3 11 3 11 0 9 A 3 12 7 16 11 1911 1910 ET 3 B, C F 5 D, E 15 17 4 8 B OMOO 3 12 | 15 | 11 - 19 D, 8 START A, 3 FINISH otros 15 0,9 G2