Question: A Hide Time Remaining A Click to see additional instructions Using the information in the table (all times are in days), the lowest extra cost

A Hide Time Remaining A Click to see additional

A Hide Time Remaining A Click to see additional instructions Using the information in the table (all times are in days), the lowest extra cost for a 20 day project is GHS Activity Normal Time Minimum Time Crash Cost (GHS/day) Predecessor A 10 8 50 B 6 3 30 c 2 2 B D 4 2 40 E 6 4 80 A F 8 5 100 DE evinis Save