Question: Click to see additional instructions The table below gives a project's activities, its predecessor(s) and the activity cost. All times are in days. Suppose the

Click to see additional instructions The table

Click to see additional instructions The table below gives a project's activities, its predecessor(s) and the activity cost. All times are in days. Suppose the project must be finished in 20 days. Normal Time Minimum Time Crash Cost (GHS/day) Activity Predecessor 10 8 50 B 6 3 30 2 2 - B D 4 2 40 E 6 80 F 8 5 100 DE Using this information, the lowest extra cost incurred for finishing the project in 20 days is GHS AD ENG HI a