Question: A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map coordinates for

A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map coordinates for the three projects are shown below. Find the ideal location (coordinates) of the supply point using Center of Gravity Method.

A highway contractor needs to locate a single

Collection point A B C Load 8,000 5,000 12,000 (X,Y) Coordinates (3,8) (7,4) (6,1)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!