Question: 5) A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map coordinates

5) A highway contractor needs to locate a single

5) A highway contractor needs to locate a single supply point to provide road building materials to three projects. The volume and the map coordinates for the three projects are shown below. Find the ideal location (coordinates) of the supply point using Center of Gravity Method. Collection point Load (X,Y) Coordinates 8,000 5,000 12,000 A B C (3,8) (7,4) (6,1)