Question: (a) How does a Tracking Gantt chart help communicate project progress? [2] (b) The following project information is available on day 25: Actual Cost is

(a) How does a Tracking Gantt chart help communicate project progress? [2] (b) The following project information is available on day 25: Actual Cost is Rs. 21,000, Earned Value is Rs. 23,000, and Planned Value is Rs. 25,000. Compute the CV and SV for the project. What is your assessment of the project on day 25? [2] (c) On day 5 a project has an earned value of Rs. 6,500 , an actual cost of Rs. 6,900 , and a planned Value of Rs. 5,800 . Compute the CV, SV and CPI for the project. What is your assessment of the project on day 5