Question: a) How much time does it save to do this project with two people instead of one person? b) How much more does it cost

a) How much time does it save to do this projecta) How much time does it save to do this project

a) How much time does it save to do this project with two people instead of one person?

b) How much more does it cost to have two people instead of one person if each person working costs $500/day?

c) Would it be worth using the second person if it would lead to a project bonus of $5,000 bonus for early delivery?...why or why not?

3) predecessor none Activity A B C optimistic 3 days 2 days 5 days 8 days 2 days most likely 4 days 2 days 6 days 10 days 4 days pessimistic 5 days 5 days 10 days 12 days 6 days none A and B A C E Potentially useful formulae: Standard deviation = V variance Z = target time finish time Standard deviation 3) predecessor none Activity A B C optimistic 3 days 2 days 5 days 8 days 2 days most likely 4 days 2 days 6 days 10 days 4 days pessimistic 5 days 5 days 10 days 12 days 6 days none A and B A C E Potentially useful formulae: Standard deviation = V variance Z = target time finish time Standard deviation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!