Question: a. How much time does it take to produce a single car? b. What is the bottleneck in this process? c. What is the steady

a. How much time does it take to produce a single car?
b. What is the bottleneck in this process?
c. What is the steady state capacity, in cars per hour, of the assembly line?
d. What is the utilization of the worker at workstation 2?
PROBLEM 2 (30 Points) Power Toys, Inc. produces a small remote-controlled toy truck on a worker-paced line consisting of nine workstations with a single worker at each station. Stations and processing times are summarized in the following table: Station Task Processing Time (seconds) 1 Mount battery units 75 2 Insert remote control receiver 85 3 Insert chip 90 4 Mount front axle 65 5 Mount back axle 70 6 Install electric motor 55 7 Connect motor to battery unit 80 8 65 Connect motor to rear axle 80 9 Mount plastic bodyStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts