Question: a is correct Problem 3.23 Question Help Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of

a is correct Problem 3.23 Question Help Usinga is correct

Problem 3.23 Question Help Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 9. a) The probability that the project will be completed in 12 months = 0014 (round your response to four decimal places). b) The probability that the project will be completed in 20 months = (round your response to four decimal places)