Question: please help Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 9 . a) The probability that the project will be completed in 12 months = (round your response to four decimal places). b) The probability that the project witt be completed in 20 months = (round your response to four docimal placos)