A job takes 72 minutes to be completed by a builder if completed with 100% efficiency. How
Fantastic news! We've Found the answer you've been seeking!
Question:
A job takes 72 minutes to be completed by a builder if completed with 100% efficiency.
How long willt the job takes if a builder completes it at 65% efficiency.