Question: A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the risk manager do next to determine risk impact of assumptions and constraints? Add the assumptions and constraints in the project charter. Add all assumptions and constraints to the risk register. Add the assumptions and constraints to the assumption log. Add the risk impact of the assumptions in the risk register