Question: A large project includes functional groups in four countries. It is close to completion, so the project manager must prepare the closeout documents. How should
A large project includes functional groups in four countries. It is close to completion, so the project manager must prepare the closeout documents.
How should the project manager obtain appropriate signoff on the acceptance of project deliverables? Select one.
Question options:
The four managers from the four countries should be asked to sign off.
The steering committee should be asked to sign off.
The project sponsor should be asked to sign off.
The director of the project managers business unit should be asked to sign off.