Question: The project manager has a large project with functional groups in four countries. Now that the project is close to completion, the project manager needs

The project manager has a large project with functional groups in four countries. Now that the project is close to completion, the project manager needs to obtain the correct signoff on the acceptance of project deliverables. What should be done to obtain the appropriate signoff on this project? Select one.

a. Ask for signoff from the managers of the four countries involved in the project.

b. Ask the project sponsor to sign off.

c. Ask the steering committee to sign off.

d. Ask the director of the project manager's business unit to sign off.