Question: A Lean Six Sigma team is working to reduce the set - up time for an operating room at a hospital. All set - up

A Lean Six Sigma team is working to reduce the set-up time for an operating room at a hospital. All set-up activities have been identified and categorized. What is the best next step?
A Move Internal Set-up Activites to Preventive Set-up
B Move External Set-up Activites to Internal Set-up
C Move Running Set-up Activites to Shut-down Set-up
D Move Internal Set-up Activites to External Set-up
E Move External Set-up Activites to Running Set-up