Question: A lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Assume it

  1. A lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Assume it takes 120 minutes for a container to circulate. (1 point)

(Note: 120 minutes = 2 hours)

  1. How many containers are required to operate this system?

  1. What is the maximum inventory that can accumulate?