Suppose a lean work center is being operated with a container size of 25 units and a

Question:

Suppose a lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Also assume it takes 180 minutes for a container to circulate.
a. How many containers are required to operate this system?
b. What is the maximum inventory that can accumulate?
c. How many kanban cards are needed?