Question: A linear programming computer package is needed. cherry cabinets, the number of hours avaliagle for the final finishing operation, and the cost per hour to

A linear programming computer package is needed.
cherry cabinets, the number of hours avaliagle for the final finishing operation, and the cost per hour to perform the work are shown here.
the cherry cabinets if it worked only on cherry cabinets.
percentage of oak cabinets assigned to cabinetmaker 3,C1= percentage of cherry cabinets assigned to cabinetmaker 1,C2= percentage of cherry cabinets assigned to cabinotmaker 2, and C3= percentage of cherry cabinets assigned to cabinetmaker 3.)
Min
01,02,03,C1,C2,C30
(c) If Cabinetmaker 1 has additional hours avallable, would the optimal solution change? Explain.
Yes, each additional hour of time for cabinetmaker 1 will reduce the total cost by $-1.75 per hour
Yes, each additional hour of time for cabinetmaker 1 will reduce the total cost by $5 per hour.
No, cobinetmaker 1 has p slack of 26.458 hours, so increasing cabinetmaker 1's time will not reduce costs.
No, cabinetmaker 1 has a slack of 37.5 hours, 50 increasing cabinetmaker 1's time will not reduce costs.
(d) If Cabinetmaker 2 has additional hours available, would the optimal solution change? Explain.
Yes, each additional hour of time for cabinetmaker 2 will reduce the total cost by $-1.75 per hour
Yes, each additional hour of time for cabinetmaker 2 will reduce the total cost by $5 per hour.
(c) Suppose Cabinetmaker 2 reduced its cost to $38 per hour. What effect would this change have on the optimal solution? Explain.
and has a value of ;
 A linear programming computer package is needed. cherry cabinets, the number

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!