Question: A loader operating has a 2 . 5 cy heaped capacity bucket and swings on a 1 . 2 - min load cycle. The trucks

A loader operating has a 2.5cy heaped capacity bucket and swings on a 1.2-min load cycle. The trucks have 11-cy capacity and a 30-min haul+ dump+return time. A 95% fill factor applies to the loader. The project works 50-min hours.
a. Determine the job production when using 5 buckets to load the trucks.
b. Calculate the unit cost in $/cy using these hourly rates: loader with operator = $90/hr, Truck with operator = $55/hour. Only need to consider the operation using 5 buckets to load the trucks.